Swift Educational Continuity in the Wake of Hurricane Ian

PROJECT PROFILE


Customer Name: Cotton Logistics

Project Location: Lee County, Cape Coral, FL

Building Type: Disaster Recovery, Education

Download Case Study

See How Mobile Modular & Cotton Logistics Quickly Set Up Schools in Florida Post-Hurricane Ian, Getting Students Back in the Classroom

Challenge

In the aftermath of Hurricane Ian in 2022, Lee County was left with a significant challenge. The storm had severely damaged the local school infrastructure, making many buildings uninhabitable. With the school year already underway, the county faced the urgent task of finding a way to continue education for countless students without delay.


Solution

To address this critical need, Cotton Logistics teamed up with Mobile Modular for their expertise in modular construction. The partnership aimed to quickly establish a temporary educational campus to house displaced students. The project involved deploying 73 modules that made up over 38,000 square feet of classroom and office space utilizing in-fleet assets.

The execution of this project was a race against time, requiring both teams to work tirelessly, including through the Thanksgiving holiday, to ensure the temporary school was ready for occupancy by the first week of December 2022. Mobile Modular provided the modular units, while Cotton Logistics handled the critical on-site services such as electrical, plumbing, and paving.

The successful completion of this project within the 30-day deadline demonstrated the effectiveness of modular construction in emergency situations, ensuring that education in Lee County could proceed without interruption. This initiative not only showcased the resilience and adaptability of the community but also highlighted the collaborative spirit and commitment of Cotton Logistics and Mobile Modular to supporting disaster recovery efforts.

Why Call Mobile Modular

By utilizing modular construction and leveraging the experience of the Mobile Modular project team, our client was able to maintain their leadership position and continue their mission to be a global frontrunner in their industry.

If you have any questions about modular building specifications, installation, turnaround time, size specifications, damage cover, insurance, contractual obligations, or adherence to building codes, browse through our comprehensive FAQs section or call us at 866-473-2495.

Our expertise, attention to detail, and end-to-end service is the reason why we continually rank high in customer satisfaction. We understand deadlines and work closely with you to deliver the unit you want on time and budget. Get your project started with Mobile Modular today!

Cotton Logistics quickly set up schools in Florida

Customer

Customer Name: Cotton Logistics

Project Location

Project Location: Lee County, Cape Coral, FL

Building Type

Building Type(s): Disaster Recovery, Education

Number

Module Count: 73

Total Area

Total Sq. Ft: 38,000 sq. ft.

Nature of Work

Nature of Work: Providing logistical support and infrastructure for disaster recovery efforts, with a focus on rapid response and implementation.

Swift Educational Continuity in the Wake of Hurricane Ian 1
Swift Educational Continuity in the Wake of Hurricane Ian 2
Swift Educational Continuity in the Wake of Hurricane Ian 3
Swift Educational Continuity in the Wake of Hurricane Ian 4
Swift Educational Continuity in the Wake of Hurricane Ian 5
Swift Educational Continuity in the Wake of Hurricane Ian 6
Swift Educational Continuity in the Wake of Hurricane Ian 7
Swift Educational Continuity in the Wake of Hurricane Ian 8
Swift Educational Continuity in the Wake of Hurricane Ian 9
Swift Educational Continuity in the Wake of Hurricane Ian 10
Swift Educational Continuity in the Wake of Hurricane Ian 11

*Click on the image to see the full-size view!

Back to top