3-Phase Design-Build Office Buildings for the Navy

PROJECT PROFILE


Project Partners: Southeast Regional Maintenance Center

Time: Four buildings in 40 days

Building Use: 4 two-story modular office buildings + Site Prep

Download Case Study

Mobile Modular Helps Increase Office Space to Accommodate the Increase in Staff of Combat Ships.

Background

We were approached by the Naval Station in Mayport, Fla., to build out a 3-phase design-build construction project. The project increased office space in order to accommodate an influx of necessary staff hired to support their littoral combat ships. The Southeast Regional Maintenance Center (SERMC) requested the use of modular office buildings for this influx. So, the experienced Mobile Modular crews assisted with the time-sensitive nature of the project.

The Three Phases of Implementation

  • Phase One: Included the installation of two buildings. Modular Mobile buit two stories tall modular offices. The office's external dimensions were 48 feet x 60 feet. It took 20 business days to install the entire building.
  • Phase Two: We delivered another two-story, 48 ft. x 60 ft. modular office building. This time completing the installation in 10 business days.
  • Phase Three: Our last phase included one more two-story, 48 ft x 60 ft office facility. We installed the final building in another 10 business days.

Scope of Work for the Design Build Office Facility

One of the major benefits of being a design-build modular construction company is that we streamline the multiple components of a project in-house. Each department of the Modular Mobile team moved swiftly to line up the logistics of engineering the buildings. We installed the necessary foundations and transported and installed the modular buildings to the site. Modular Mobile then finished the project with sprinkler systems, the foundation deck tower, and all facility steps and ramps.

For a more comprehensive list of our roles in the Naval Station Mayport facility, see below:

  • Manufacturing of modular buildings
  • Delivery of modular building systems to the site
  • Installation of structural concrete for building foundations
  • Installation of structural concrete for stair towers/ramps
  • Crane installation to aid modular buildings and their structural connections
  • Installation of exterior & interior mate-line finishes
  • Installation of perimeter skirting
  • Installation of sprinkler system
  • Installation of the two-story aluminum stair towers and ramps including structural connections.
  • Manufacturing of the modular buildings system
  • Delivery of modular building systems to the site
  • Installation of structural concrete for building foundations
  • Installation of structural concrete for stair towers/ramps
  • Crane installation to aid modular buildings and their structural connections
  • Installation of exterior & interior mate-line finishes
  • Installation of perimeter skirting
  • Installation of sprinkler system
  • Installation of the two-story aluminum stair towers and ramps including structural connections

Why Call Mobile Modular

By utilizing modular construction and leveraging the experience of the Mobile Modular project team, our client was able to maintain their leadership position and continue their mission to be a global frontrunner in their industry.

If you have any questions about modular building specifications, installation, turnaround time, size specifications, damage cover, insurance, contractual obligations, or adherence to building codes, browse through our comprehensive FAQs section or call us at 866-473-2495.

Our expertise, attention to detail, and end-to-end service is the reason why we continually rank high in customer satisfaction. We understand deadlines and work closely with you to deliver the unit you want on time and budget. Get your project started with Mobile Modular today!

MODULAR BUILDING INSTITUTE AWARD OF DISTINCTION

WINNER OF THE MODULAR BUILDING INSTITUTE AWARD OF DISTINCTION

Design-Build Construction Project for the SERMC Facility

Customer

Customer Name: Naval Station Mayport - SERMC Facility

Project Location

Project Location: Mayport, Fla.

Info

Project Size: (4) two-story modular office buildings + Site Prep and Finish Projects

Dimensions

Dimensions per Building: 48x60 on each floor - total 5,720 sq. ft. per building

Total Area

Total Sq. Ft: 22,880 sq. ft.

Job Type

Job Type: Lease

3-Phase Design-Build Office Buildings for the Navy 1
3-Phase Design-Build Office Buildings for the Navy 2
3-Phase Design-Build Office Buildings for the Navy 3
3-Phase Design-Build Office Buildings for the Navy 4
3-Phase Design-Build Office Buildings for the Navy 5
3-Phase Design-Build Office Buildings for the Navy 6
3-Phase Design-Build Office Buildings for the Navy 7
3-Phase Design-Build Office Buildings for the Navy 8
3-Phase Design-Build Office Buildings for the Navy 9
3-Phase Design-Build Office Buildings for the Navy 10
3-Phase Design-Build Office Buildings for the Navy 11
3-Phase Design-Build Office Buildings for the Navy 12

*Click on the image to see the full-size view!

Back to top